Final countdown. We have the blessing March 5, 2017!
Just little details to finish.
Kitchen Renovation, 01/11/17:
Flooring is in, Counter tops going in next Wednesday! Wiring you see coming out of the floor in the center will give power outlet on the island.
Update 12/26/16: Cabinets are in. Flooring and counter tops ordered.
Kitchen Renovation Update, November 18
The drywall has been installed. Waiting inspection and then we can tape and move on!
Kitchen Renovation Update, November 13, 2016
Since most of the work done between now and the previous update was electrical and plumbing and not readily discernible to the average person, pictures don’t tell much. Now we’ve passed the county inspection and the insulation and vapor barrier have been installed. Next step: Dry Wall!
Kitchen Renovation Update, September 29, 2016
Thank you Hefti Brunold, Dennis Lipska and Bob Lloyd for stepping into the breach and continuing the work on our kitchen renovation!
Light boxes are in and ready for light fixtures
Framing for new pocket doors
Kitchen Renovation Update, September 8, 2016
The frame for the pass-through wall is up!
Kitchen Renovation Update, September 5, 2016
Not much except electrical work done.
The box. Waiting for lights.
Kitchen Renovation Update, August 17, 2016
Ready and waiting for the new electrical
Oops, did you notice the pass through wall is entirely gone? When the sheetrock was removed, it was discovered the frame didn’t meet code. So that one has to be rebuilt from the base up!
The cabinets have arrived! It’ll be like Christmas to open each box! Then it’ll be like a jigsaw puzzle to find where every item goes!
_____
Kitchen Renovation Update, August 10, 2016
Big thank you to Hefti Brunold for all the days and days he’s been faithfully working on the project.
We do have running water outside, just cold.
Last week, pocket door exposed, this week, gone for good. Can’t wait to see the new ones.
D
Down to the bare bones here in prep for the new pass through window and pocket door. Can’t wait to start building it back.
The ceiling is exposed, ready for new wiring for new lights. Note the insulation is gone from the walls, also in prep for new wiring.
——
Kitchen Renovation Update, August 3, 2016
What’s behind the curtain? Tools!
The pass-through opening before the new pocket door is installed:
The truth behind pocket doors. Do these have to be changed to accommodate the new refrigerator? Stay tuned.
——
Kitchen Remodel Update July 27, 2016
A blank slate: Lights will go next, and soon the garage door at the pass-through window. A pocket door will replace that.
Hefti, hard at work!
——
Kitchen Remodel Update, July 20, 2016
The stove sold. Didn’t it seem that it was bigger than that space? While we didn’t get as much as expected when selling it, thanks to Pastor Gene’s finding some great deals on appliances, we are overall still below budget.
——
Kitchen Remodel Update July 13, 2016
Kitchen Remodel Update: The over-the-stove vent has been removed. The Wolf stove has been placed up for sale on eBay and Craig’s List. We have ordered the appliances and cabinets and by the time you read this our new refrigerator will have arrived. Until we are ready to move it into the kitchen, we will use it from the Fellowship Hall. The old refrigerator has been given away.
We expect to take out the upper cabinets this coming week and then the lower cabinets. Once those are gone, work on the pass-through window and new pocket door will begin. If you wish to have any of the cabinets, please let Pastor Gene or Barbara McMahon know.
Pictures of the progress are being posted on the website. Let Barbara McMahon know if you have any questions. Thank you again and again to all who have pledge money for this project and are so faithful in honoring that pledge.